Our first visit to Zatric site, end of
September 2000 and every where is just flat surface with garbage.

Few days later we start to digging first hole
for the concrete base of the 42 meter mast-tower and in the background you can see German
KFOR radio surveillance vehicle.

Zatric site visible from the valley.

Mike Furlong, General Project Manager helping
in fixing mad road to help "BIG BEAST" reach destination. Top secret code name for 12 meter long container was BIG BEAST.

Driver of crane on the left, Faton, Rudolf and
Mike.Many thanks to Faton, from Mabetex. With his great help "BIG BEAST was
delivered on the top of Zatric.

Great help from Faton, always work at
Sundays and night if nessesery. Thank you Faton.
Mike Furlong and cloud behind him on Zatric
site.The cloud is one special cloud.

Two great friends Mike and Rudolf on Zatric
site.We start MISSION IMPOSSIBLE on Zatric
site.

Zatric mast-tower in the middle of his height.

Detail of 42 meter Zatric mast-tower when FM
radio antennas are installed.

Complete working view of Zatric site.

Detail of four foot concrete base and
generator container.

Preparing to put generator container on his
concrete base, Januz, Rudolf and other people from Mabetex.

Angelo, Ido and Rudolf precise feeder
installation.

Rudolf and Ivan in Zatric container, at back
side of equipment doing installation. |